Tuesday, April 20, 2010

DOWNTOWN ANGOLA CONSTRUCTION SCHEDULE FOR WEEK OF: April 19th

Contact: Julie Cole, City Planner. City of Angola, Indiana
Telephone: (260) 665-7465
Email: jcole@angolain.org

###

The following construction schedule is planned for the week of April 19th. We will make every attempt to follow this schedule but it is subject to change and weather permitting.
The following items will be addressed:

Mon. – Finish planters, start rubbing finish on planters, and start underlayment in northeast quadrant. Topsoil planters.

Tues. – Continue pouring underlayment, continue to rub planters, and ADA ramps.
 
Wed. – Finish all concrete in north east quadrant and start curbing in northwest quadrant.
 
Thursday – Continue pouring curbing
 
Friday – Finish curbing in northwest quadrant, start planters.


The following north quadrant businesses have an alternate side or rear entrance:
Angola City Hall
Sutton’s Deli
Stewart Law
Calicos & Collectibles
Jitterbug Photography
Coachlight Coffee House
Hansbarger Realty
Pizza Forum
Bent Fork Art Studio

The City of Angola is committed to making sure the Public Square project is completed on schedule in a safe, timely and efficient manner. Weekly construction schedule updates will be made available every week.

The City of Angola appreciates your continued cooperation as these improvements are made. Parking will be restricted in one or both of the north quadrants the week of April 19th, however access to downtown businesses will be maintained at all times. All downtown businesses will remain open throughout the duration of this improvement project.

No comments:

Post a Comment