Downtown Construction Update May 3rd

DOWNTOWN ANGOLA CONSTRUCTION SCHEDULE FOR WEEK OF:
May 3rd

Contact: Julie Cole, City Planner. City of Angola, Indiana
Telephone: (260) 665-7465
Email: jcole@angolain.org
###
The following construction schedule is planned for the week of May 3rd. We will make every attempt to follow this schedule but it is subject to change.

Monday (05/3)
Continue pouring planters in Northwest quadrant
Finish demolition in the Southwest quadrant and install proposed storm sewer just beyond the easterly curb line

Tuesday (05/04)
Continue pouring planters in Northwest quadrant
Stake and layout for storm, lights and curbs
Start prepping for curb and gutter in Southwest quadrant

Wednesday (05/05)
Finish pouring planters, curb and gutter. Start pouring ADA ramps in Northwest quadrant
Continue prepping for curb and gutter in Southwest quadrant
Install new light foundations and conduit in Southwest quadrant

Thursday (05/06)
Start pouring sidewalks and underlayment in the Northwest quadrant
Re-cut and prep for asphalt in Northwest quadrant
Continue prepping for concrete in Southwest quadrant

Friday (5/07)
Finish all concrete in Northwest quadrant
Clean up Northwest quadrant

The following North quadrant businesses have an alternate side or rear entrance:
Angola City Hall
Sutton’s Deli
Stewart Law

The South quadrant businesses will remain open during construction.
The City of Angola is committed to making sure the Public Square project is completed on schedule in a safe,Timely and efficient manner. Weekly construction schedule updates will continue to be made available. The City of Angola appreciates your continued cooperation as these improvements are made. Parking will Restricted but all downtown business will remain open throughout the duration of this improvement project.