DOWNTOWN ANGOLA CONSTRUCTION SCHEDULE FOR WEEK OF: May 31st

DOWNTOWN ANGOLA CONSTRUCTION SCHEDULE FOR WEEK OF:
May 31st

Contact: Julie Cole, City Planner. City of Angola, Indiana
Telephone: (260) 665-7465
Email: HYPERLINK "mailto:jcole@angolain.org" jcole@angolain.org
**WEATHER PERMITTING**
The following construction schedule is planned for the week of May 31st. We will make every attempt to follow this schedule but it is subject to change.

Monday (05/31)
**Holiday- No work will be completed

Tuesday (06/01)
Start forming and pouring curb and gutter in Southeast Quadrant
Continue paver installation in Northwest Quadrant

Wednesday (06/02)
Continue to form and pour curb and gutter and start forming and pouring planters in the Southeast Quadrant
Continue brick paver installation in Northwest Quadrant
Pave Southwest Quadrant

Thursday (06/03)
Finish pouring curb and gutter, pour new concrete banding and continue to form and pour planters
Continue brick paver installation in Northwest Quadrant

Friday (06/04)
Continue to form and pour planters and start pouring underlayment and sidewalk
Continue brick paver installation in Northwest Quadrant
Start placing topsoil in planters for Southeast Quadrant



The following North Quadrant businesses have an alternate side or rear entrance:
Angola City Hall
Sutton’s Deli
Stewart Law
The South Quadrant businesses will remain open during construction.

The City of Angola is committed to making sure the Public Square project is completed on schedule in a safe,
Timely and efficient manner. Weekly construction schedule updates will continue to be made available.
The City of Angola appreciates your continued cooperation as these improvements are made. Parking will be
Restricted but all downtown business will remain open throughout the duration of this improvement project.